Electric truck charging at your plant
E-mobility
DC fast charging for electric trucks inside your yard. What decides the project is not the charger: it is the medium-voltage service, the transformer and the protection that feed it.
The power at stake
A semi-truck that has to head out again in a few hours needs DC charging, in what Agreement A/108/2024 (Acuerdo A/108/2024) classifies as mode 4. This is high-power equipment fed from a dedicated transformer or from the plant's substation.
Four 350 kW chargers add up to 1.4 MW if they run at the same time (illustrative example). For many plants that is a large share of their contracted demand, and it forces a review of the medium-voltage service before buying a single charger.




Medium voltage
If the available capacity falls short, truck charging means a load increase or a new connection. Agreement A/108/2024, issued by the then CRE (DOF September 10, 2024), refers the connection of charging infrastructure to the load-center regulatory manual (Manual Regulatorio de Centros de Carga) of the Grid Code (Código de Red): below 69 kV it is handled with the Supplier or the Distributor and from 69 kV with CENACE. It is advisable to confirm the current process with the CNE.
Inside the fence line the scope is a substation: medium-voltage switchgear, a dedicated or upgraded transformer, panels, protection coordination, grounding and raceways to each charger. Each charging circuit is protected under article 625 of NOM-001-SEDE-2012, with overcurrent protection for continuous duty of no less than 125 % of the equipment's maximum load and a lockable disconnecting means.
High-power chargers are power electronics. Like any load of that type, it is worth reviewing their effect on the plant's power quality and on Grid Code compliance before connecting them.
Battery and solar
A battery bank charges slowly from the grid, or from on-site solar generation, and delivers the high power during the truck's charging session. That way the point of connection sees a smaller peak. It is an alternative to expanding the substation, or a way to wait for the load increase without stopping yard operations.
Three scenarios are compared with numbers: expand the substation, install a battery, or limit power through load management and accept longer sessions. The answer depends on your measured load curve and your yard operations, not on a preference for a technology.
What we do
We start with your bill, metering at the point of connection and yard operations: how many trucks, at what time and for how long they can stay plugged in.
Available capacity at the point of connection, measured load curve and power scenarios.
Substation, transformer, protection, grounding and power quality studies.
Load increase or new connection with the Supplier, the Distributor or CENACE, depending on voltage.
DC chargers, battery and solar if the scenario includes them, civil and electrical works, and commissioning.
Under a GTO Vigía contract: chargers, substation and battery with one accountable partner.
Questions
When it is not for you
If your trucks spend the night in the yard and have hours to spare for charging, high-power DC fast charging may be unnecessary. Lower-power chargers and load management ask much less of the substation.
If the yard is not yours or your lease does not allow you to expand the substation, resolve that before the electrical project. The medium-voltage investment stays with the property.
And if the number of electric trucks is not decided yet, do not size the substation for an imaginary fleet. The raceways can be left ready and you can grow in stages.
How we work
Seven-day campaign with a Class A analyzer.
Engineering based on your real load curve.
Supply and installation inside your fence line.
GTO Vigía sustains the result after construction.

Energy solutions
In a short meeting we review your bill with you, on screen, and tell you what is worth measuring.
We work with plants on medium and high voltage. By sending you accept our privacy notice.
Strengths
GTO Energy offers electrical engineering tailored to your plant. Request your diagnostic and start by knowing where the opportunity is.
Fully creditable if you implement. No charge if we find no package that pays back in under 4 years.
Compliance reports based on RES/550/2021, filed with the CNE and CENACE.
We service plants installed by others, starting with a condition survey.
Partners with trademark-use authorization


Group clients since 1983





Also: Cuadritos, Productora Nacional de Papel and Telemar.