GTO Energy · Energy Experts Contact
Skid-mounted industrial diesel backup generator, ready for backup.

Backup Generators

Storage and Backup

Who it applies to
Processes with critical loads that cannot tolerate long outages, and backup obligations
What we size
The critical load, not the total demand. It is the decision that sets the cost
Transfer type
With a gap or uninterrupted, depending on what your process tolerates
Framework
Backup under article 32 of the Electricity Sector Law (Ley del Sector Eléctrico) when it applies to you
Timeline
2 to 5 months
Operation
Periodic testing under a GTO Vigía reliability contract

Fuel-based backup, for what cannot wait on a battery

Backup generators sized on your real critical load, not on the plant's total demand. That distinction is the difference between equipment that pays for itself and one that starts once a month for nothing.

Generator or battery?What a critical load isThe equipment nobody testsWhen it is not for you

The right question

It is not generator or battery. It is what each one does.

A battery bank provides very good backup for minutes and hours, and it also cuts your billable peak every day of the year. A backup generator does not save you a single peso in normal operation, but it sustains your process during a long outage for as long as the fuel lasts.

They answer different questions. The battery solves gapless transfer and cost; the generator solves duration. In many projects the right answer is the combination, and in several the right answer is only one of the two.

What decides it is which loads are critical, how long they must be sustained and what your process tolerates at the instant of transfer. Three questions, and none of them is answered with annual consumption.

01

What the battery does

Uninterrupted transfer, cutting the billable peak every day, and backup from minutes to hours.

02

What the generator does

Sustains the critical load during a prolonged outage, as long as there is fuel.

03

What the combination does

The battery covers the instant and the cost; the generator covers the duration. They are sized together.

If someone quotes you a backup generator without having asked what your critical loads are, they are selling you capacity, not backup.

Battery storage.
Battery storage
Backup generator.
Backup generator
Switchgear and protection.
Switchgear and protection
Point of connection.
Point of connection

What a critical load is

Four questions before sizing

01

What stops and what can wait?

Backing up the entire plant costs several times more than backing up what truly cannot stop. The list is made with your process people, not with a catalog.

02

How long does it need to be sustained?

Half an hour to carry out a safe shutdown is not the same as eight hours to keep producing. It defines the tank and the equipment.

03

Does it tolerate a gap during transfer?

A motor tolerates it; a server and a PLC often do not. That determines whether the transfer needs intermediate storage.

04

Is the backup a response to an obligation?

Article 32 of the Electricity Sector Law requires backup in certain cases. If it applies to you, the sizing has conditions that are not optional.

How it is verified

With those four answers and your measured load profile, the sizing follows. Without them, any proposed capacity is a guess with a price tag.

The equipment nobody tests

A backup generator without testing is an expensive guess

The most common failure mode of backup equipment is not that it breaks down: it is that nobody knows it is broken. It has gone months without starting under load, the starter battery has sulfated, the fuel has degraded, and that is discovered on the day of the outage.

That is why every generator we deliver comes with its proposed testing program from day one: start under load at a defined frequency, review of the starting and fuel systems, and a record of every test.

Under a reliability contract we carry out those tests and you receive the report. Without a contract we leave them to you in writing, because we would rather someone else does them than nobody.

What the testing program includes

Start under load at a defined frequency · condition of the starting system and battery · fuel quality and level · transfer actually tested, not simulated · dated record of every test, which is what counts when someone asks.

When it is not for you

What we will tell you not to do

We tell you at the first meeting

If your critical load is small and what you need is minutes of autonomy to carry out a safe shutdown, a properly sized battery bank costs you less and gives you gapless transfer. We are not going to sell you an engine.

If what you want is to lower your bill, a backup generator is not the way: it does not save you a single peso in normal operation. That is what storage is for.

If you already have a generator installed and do not know whether it works, start there. A load test costs a fraction of new equipment and often the answer is that yours is fine.

How we work

One accountable partner, from metering to operation

We measure

Seven-day campaign with a Class A analyzer.

We design

Engineering based on your real load curve.

We build

Supply and installation inside your fence line.

We operate

GTO Vigía sustains the result after construction.

Download Brochure

Energy solutions

Download here

Interested in a storage project?

In a short meeting we review your bill with you, on screen, and tell you what is worth measuring.

We work with plants on medium and high voltage. By sending you accept our privacy notice.

Strengths

What backs every project

GTO Energy offers electrical engineering tailored to your plant. Request your diagnostic and start by knowing where the opportunity is.

01

We measure before we propose

Seven days with a Class A analyzer at your facility, before quoting.

02

One accountable partner

Engineering, supply and installation inside your fence line.

03

Diagnostic with no down payment

Fully creditable if you implement. No finding, no charge.

04

Current regulation

Compliance reports based on RES/550/2021, filed with the CNE and CENACE.

05

Operation and maintenance

GTO Vigía: monitoring, monthly reporting and priority service.

06

Third-party systems

We service plants installed by others, starting with a condition survey.