Charging stations as a business
E-mobility
Engineering for those who want to start a public charging business: site feasibility, sizing, billing model, permits, construction and operation. No made-up return figures.
Feasibility
A property where people stop for as long as a charge takes: highway, shopping center, service area. Agreement A/108/2024 (Acuerdo A/108/2024) requires at least mode 3 or mode 4 charging on highways.
It is verified with the Supplier or the Distributor before committing to the property. Without capacity, the business depends on grid works whose timeline and cost you do not control.
Electric vehicles that pass by and need to charge there. Infrastructure does not create demand; it serves it. That number has to be backed by a market study, not by our engineering.
A generic return on investment. It depends on the site's real traffic, the price you can charge, the cost of energy on your tariff and charger utilization. We give you the model with those variables so you set the assumptions and see what happens if they are not met.




Regulatory framework
Agreement A/108/2024, issued by the former CRE (DOF September 10, 2024), regulates the connection of charging infrastructure to the National Electric System (Sistema Eléctrico Nacional) and defines a charging station as a service station with charging infrastructure on a property, where the service is charged for (section 3.17). Under its chapter 6, selling energy at charging stations does not require a permit: it requires a notice to the regulator within six months of receiving supply. After the 2025 reform the regulator is the CNE, and it is advisable to confirm the current procedure with it.
The same chapter requires the price to be visible to the user, in pesos per kWh or by time or charging period. The connection follows the Grid Code's (Código de Red) load-center regulatory manual (Manual Regulatorio de Centros de Carga): below 69 kV it is handled with the Supplier or the Distributor, and from 69 kV with CENACE.
The Regulations of the Electricity Sector Law (Reglamento de la Ley del Sector Eléctrico, DOF October 3, 2025) devote articles 196 to 200 to e-mobility, and its Ninth transitory article establishes that, until official standards for charging infrastructure exist, the applicable Mexican standards and international standards are followed. Article 625 of NOM-001-SEDE-2012 governs the electrical installation.
Revenue model
The user pays for the energy received. It is easy to explain and compares directly with the cost of energy on your bill. It requires reliable metering per session.
The user pays for the time connected. It discourages an already charged vehicle from occupying the space, but penalizes anyone whose vehicle charges slowly.
The tariff CFE bills the site under, including the demand charge, is your cost. A fast charger that is rarely used can set a demand that you pay for all month.
What we do
We handle the engineering, supply, installation and operation. The market study and the investment decision are yours; we build the model that supports it with you.
Available capacity at the point of connection, scope of grid works and site requirements.
Number, type and power of chargers; battery or solar if the scenario justifies it; cost model with your traffic assumptions.
Connection request and energy-sales notice to the regulator, confirming the current procedure with the CNE.
Substation or service entrance, chargers, protection per article 625, civil works and commissioning.
Charger availability, maintenance, fault response and reporting of energy sold and demand.
Questions
When it is not for you
If you have not verified the available capacity at the point of connection, do not buy chargers or sign for the property. Grid works that were not in the plan can change the entire business case.
If the site has no traffic of electric vehicles that need to charge there, the chargers will not create it. An underused charging station pays its demand charge just the same.
And if what you are after is a guaranteed return, this is not the project: revenue depends on utilization, and engineering does not control utilization.
How we work
Seven-day campaign with a Class A analyzer.
Engineering based on your real load curve.
Supply and installation inside your fence line.
GTO Vigía sustains the result after construction.

Energy solutions
In a short meeting we review your bill with you, on screen, and tell you what is worth measuring.
We work with plants on medium and high voltage. By sending you accept our privacy notice.
Strengths
GTO Energy offers electrical engineering tailored to your plant. Request your diagnostic and start by knowing where the opportunity is.
Fully creditable if you implement. No charge if we find no package that pays back in under 4 years.
Compliance reports based on RES/550/2021, filed with the CNE and CENACE.
We service plants installed by others, starting with a condition survey.
Partners with trademark-use authorization


Group clients since 1983





Also: Cuadritos, Productora Nacional de Papel and Telemar.