Paper, cardboard and packaging
Industries
Paper mills, corrugators, converters and packaging plants. Three-shift operations with large motors and, often, a boiler that never shuts down.
This sector's problem
Pumps, refiners, rolls and extractors: the load is motors, many of them large and some oversized. The most common result is a low power factor and a demand set by the starts.
At the same time, the plant buys gas to produce drying steam, almost always continuously. Electricity and heat are bought separately, when a single machine could produce both.
That is the entry condition for cogeneration. It does not guarantee it will pay off, but it obliges you to evaluate it with your own plant's numbers.
Inventory and measurement of the main motors: actual load, starts and power factor per unit.
Power factor and, where there are drives, harmonics. Based on measurement, not on the bill average.
How much steam you use, at what pressure and on what schedule. It is the basis for deciding whether cogeneration pays off.




Signs it applies
The entry condition for cogeneration. That is where the evaluation starts.
Motors running lightly loaded. It is fixed without major construction.
There is a sequencing or starter adjustment that lowers demand without touching production.
They lose efficiency and run hot. They are measured before deciding which to replace.
In an initial review, with your bill on screen, we tell you what is worth measuring and what we would expect to find.
What to do first
Motor and power factor measurement first. It is the cheapest step and the one that lowers the bill the following month.
Then the heat balance: how much steam, at what pressure and for how many hours a year. That decides whether cogeneration pays off in your plant, and at what size.
Infrastructure last: substation, switchgear and protection sized for what the operation truly needs.
We handle the thermal engineering with specialized partner firms. We do not improvise it and we do not pretend to do it alone.
When it is not for you
If your plant only converts or prints and does not use steam, cogeneration does not pay for itself. There the work is on motors and power factor.
If you were offered to replace all the motors at once, first ask for the load measurement of each one. Often it makes sense to replace some and adjust others.
How we work
Seven-day campaign with a Class A analyzer.
Engineering based on your real load curve.
Supply and installation inside your fence line.
GTO Vigía sustains the result after construction.

Energy solutions
In a short meeting we review your bill with you, on screen, and tell you what is worth measuring.
We work with plants on medium and high voltage. By sending you accept our privacy notice.
Strengths
GTO Energy offers electrical engineering tailored to your plant. Request your diagnostic and start by knowing where the opportunity is.
Fully creditable if you implement. No charge if we find no package that pays back in under 4 years.
Compliance reports based on RES/550/2021, filed with the CNE and CENACE.
We service plants installed by others, starting with a condition survey.
Partners with trademark-use authorization