Four ways to pay for an energy project, and who carries the risk in each one

The technical conversation is usually settled long before the financial one, and projects fall apart on the money side. These are the four real structures, with the question that sets them apart: who owns the asset and who answers if it underperforms.

Handshake over a solar array when closing a deal.
The question is not how much it costs, but who carries each risk for twenty years.

The question that sorts all four

It is not "how much does it cost?". It is who owns the asset, and who answers if it does not produce what was promised? Those two answers determine the price, the accounting treatment, the term and what happens when the contract ends.

Everything else —trade names included— is a variant of those two. And it is worth knowing, because the sector regularly produces new acronyms, and almost all of them fall into one of these four boxes.

1 · Own CAPEX

You buy the system. You own it from day one, keep one hundred percent of the savings, and carry the performance risk: if it produces less than projected, the difference is yours.

It is the structure with the best return and the one that requires the most capital. It is also the one that depends most on the sizing being correct, because there is no third party with an incentive for the system to perform.

Here the contractual performance guarantee and the operating contract are not extras: they are what replaces the partner who in other schemes would have skin in the game.

2 · Leasing

A third party buys the equipment and you pay rent to use it, usually with a purchase option at the end. You keep the full savings, minus the rent.

The performance risk is still yours: the lessor collects the rent whatever the system produces. It is equipment financing, not results financing, and it is best not to confuse the two.

Its real advantage is on the balance sheet and cash flow, not on risk. And the accounting and tax treatment of a lease depends on how it is structured: your accountant defines that, and it is worth defining before signing, not after.

Figure 1
Four structures, two questions: who owns it and who answers if it underperforms
StructureAsset ownershipPerformance riskCash-flow effectAt the end of the contract
Own CAPEXYou, from day oneYou: if it produces less, the difference is yoursRequires the full capital up front; you keep 100 % of the savingsThe asset is already yours; there is no contract to expire
LeasingA third party (the lessor) during the termYou: the rent is paid whatever it producesNo up-front equipment purchase; you keep the savings, minus the rentUsually, a purchase option
PPA · power purchaseThe third party that investsThe owner: if it produces less, it bills lessNo capital; you pay each kWh at an agreed price, with its escalation formulaSet by the contract: transfer, renewal or removal of the equipment
Energy as a serviceThe third party, which also operates and maintainsThe third party, which commonly commits to availabilityNo capital; operating expense per service, with the smallest savings marginSet by the contract: transfer, renewal or removal of the equipment
Going down, the performance risk shifts from you to the third party, and the savings margin left to you shrinks. These are market practices, not rules: the accounting and tax treatment of each is defined by your accountant with the contract in hand.

3 · PPA · power purchase agreement

A third party invests, owns the system and sells you the energy it produces, at an agreed price per kilowatt-hour that is usually below your current tariff. You put in no capital.

Here the risk does shift: if the system produces less, the owner bills less. That is the real appeal of the scheme, more than the zero capital.

In exchange, you sign a long-term purchase commitment — fifteen or twenty years is common — and that is what must be read carefully. The price per kilowatt-hour, its escalation formula, what happens if you want to terminate early, what happens if you relocate or close the plant, and who owns the system at expiry.

And a regulatory point worth checking in any structure that contemplates selling surplus energy: the Electricity Sector Law (Ley del Sector Eléctrico) establishes that, in interconnected self-supply, surplus energy is sold exclusively to the state-owned public utility. If a scheme promises to let you sell energy to third parties, ask for the legal basis.

4 · Energy as a service

It is an extended PPA: the third party not only sells you the energy, it also operates and maintains, and commonly commits to availability. You pay for the service received.

It is the structure that shifts the most risk and, consistently, the one with the smallest savings margin for you — because risk has a price and someone is charging it.

It makes sense when continuity is worth more than savings, when you have no in-house team to operate the asset, or when the committee will not approve capital but will approve an operating expense with a committed result.

What changes the decision and nobody asks in time

How long you will be at that site. A twenty-year commitment on a property leased for five is a problem discovered late. It is the question that should stop the most projects and is almost never asked at the first meeting.

Whether the savings are compared against the right tariff. A price per kilowatt-hour compared against your average cost looks better than it is. The honest comparison is against the effective cost of the energy that system actually replaces, in the hours when it replaces it.

What happens at the end. Asset transfer, renewal, equipment removal, the condition the roof is handed back in. It is in the contract and almost nobody reads it until year fourteen.

The accounting and tax treatment. We do not define it and we will not tell you a scheme is "one hundred percent deductible". Your accountant defines it with the contract in hand.

Figure 2
Twenty years of commitment, with decisions spread across the term
PPA · 20 YEARS Signing Early exit window Expiry Asset transfer Each mark: price escalation per formula Year 14: the final clause gets read Property lease 5 YEARS And the other fifteen? YEAR 0 5 10 15 YEAR 20
On a property leased for five years, a twenty-year PPA leaves fifteen years uncovered. The position of the exit window and the escalation frequency vary with each contract; here they are illustrative.

What we do and what we do not

We size and execute. We are not a financial firm and we will not recommend a structure as if we were neutral about it.

What we do is two useful things: we tell you how big the opportunity is with the metering in hand, which is the data every structure depends on, and we introduce you to the financing channels we work with so you can negotiate directly.

And we tell you when no structure fixes the project. If the sizing is wrong, the best financial scheme in the world only spreads a disappointment over twenty years.

Sources

Electricity Sector Law (Ley del Sector Eléctrico), DOF March 18, 2025 · Regulations of the Electricity Sector Law, DOF October 3, 2025. Article 32, sections I to III, on the sale of surplus energy in interconnected self-supply.

The characteristics of each financial structure are market practice, not regulation. The only thing this article states on a legal basis is the exclusivity of surplus energy sales.

How to compare two proposals with different schemes

Put both in the same table with four rows: who owns it, who answers if it does not produce, what you pay in total over the term, and what you keep at the end. Almost always one of the two falls apart on its own.

Keep reading

Related

Download Brochure

Energy solutions

Download here

Would you like to know where your plant overspends?

In a short meeting we review your bill with you, on screen, and tell you what is worth measuring.

We work with plants on medium and high voltage. By sending you accept our privacy notice.

Strengths

What backs every project

GTO Energy offers electrical engineering tailored to your plant. Request your diagnostic and start by knowing where the opportunity is.

01

We measure before we propose

Seven days with a Class A analyzer at your facility, before quoting.

02

One accountable partner

Engineering, supply and installation inside your fence line.

03

Diagnostic with no down payment

Fully creditable if you implement. No finding, no charge.

04

Current regulation

Compliance reports based on RES/550/2021, filed with the CNE and CENACE.

05

Operation and maintenance

GTO Vigía: monitoring, monthly reporting and priority service.

06

Third-party systems

We service plants installed by others, starting with a condition survey.